Saturday 29 January 2022

Goodyear, AZ (EMR) O/B Pool Deliberations - UPDATE - Construction/Destruction Has Begun!

UPDATE 1-24-2022:
Excavation completed in 1 day!

UPDATE 1-4-2022:
Excavation scheduled for 01-24-22!

UPDATE 11-17-2021:
Received city permits and HOA approval. Started receiving bids from trades.

Final actual plan (shorter shallow-end bench than the 3-D picture below).
Screenshot 2021-11-17 085213.jpg

Pretty close to final plan design
Screenshot 2021-11-17 084923.jpg

UPDATE 09-27-2021: :)
Design updated and ready for our approval...

Read more